ST- 246: 2010 Trail Repairs and Resurfacing

 

NCDOT # U-4726 HI

This project will be funded by the American Recovery and Reinvestment Act (ARRA).

ST-246 Project Manual and Details

Contract ST-246, Project: 2010 Trail Repairs and Resurfacing was awarded to Asphalt Experts of Durham, N.C. on November 19, 2009 with NCDOT Concurrence of Award on December 3, 2009. Contract execution was completed on December 15, 2009. The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for repairs and resurfacing of portions of the American Tobacco Trail, North-South Greenway Trail, and Riddle Road Spur Trail. The project manual, plans, addenda and other reporting information are available on this site.

Bid Information

City of Durham Street Construction Specifications and Water and Sewer Construction Specifications are available for download – free of charge.

For project ST-246, all contractors bidding on the project must be pre-qualified by NCDOT as EITHER "pre-qualified bidder" OR "subcontractor" in order to be considered for contract award.
Contractors pre-qualified by NCDOT

In addition, all prime contractors must have a Dun and Bradstreet D-U-N-S Number in order for ARRA reporting to be accurate.

Each bidder must be licensed under Chapter 87 of the N.C. General Statutes as a General Contractor and holding a Highway classification. The City Council of the City of Durham reserves the right to reject any or all bids. All bids must include a non-collusion affidavit.

Disadvantaged Business Enterprise

The Disadvantaged Business Enterprise (DBE) goal for this project is 6 percent.

Subcontractors must be certified by NCDOT as a DBE in order for their participation to count towards the goal.
DBEs certified by NCDOT

Davis-Bacon Prevailing Wage Rates (Section 1606) - Prevailing wage rate requirements apply to all ARRA-funded construction projects.

Important Bid Download Notice

To ensure that all bidders using the City's Web Site are kept up to date on any addendums, changes, or informational notices; please send an e-mail to Tim Jackson indicating which bid was downloaded. Failure to complete this important step may render your bid as non-responsive.

Anticipated Schedule

Wednesday, October 21, 2009     Pre-Construction Meeting at 2 p.m.
Thursday, October 29, 2009        Bid Opening at 2 p.m.
Thursday, November 19, 2009     Award Date
December 3, 2009                     NCDOT Concurrence of Award
February 2010                          Pre-Construction Meeting
March 2010                              Begin Work
June 2010                                Work Complete

 