This project will be funded by the American Recovery and Reinvestment Act (ARRA).
ST-246 Project Manual and Details
Contract ST-246, Project: 2010 Trail Repairs and Resurfacing was awarded to Asphalt Experts of Durham, N.C. on November 19, 2009 with NCDOT Concurrence of Award on December 3, 2009. Contract execution was completed on December 15, 2009. The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for repairs and resurfacing of portions of the American Tobacco Trail, North-South Greenway Trail, and Riddle Road Spur Trail. The project manual, plans, addenda and other reporting information are available on this site.
City of Durham Street Construction Specifications and Water and Sewer Construction Specifications are available for download – free of charge.
For project ST-246, all contractors bidding on the project must be pre-qualified by NCDOT as EITHER "pre-qualified bidder" OR "subcontractor" in order to be considered for contract award.
Contractors pre-qualified by NCDOT
In addition, all prime contractors must have a Dun and Bradstreet D-U-N-S Number in order for ARRA reporting to be accurate.
Each bidder must be licensed under Chapter 87 of the N.C. General Statutes as a General Contractor and holding a Highway classification. The City Council of the City of Durham reserves the right to reject any or all bids. All bids must include a non-collusion affidavit.
The Disadvantaged Business Enterprise (DBE) goal for this project is 6 percent.
Subcontractors must be certified by NCDOT as a DBE in order for their participation to count towards the goal.
DBEs certified by NCDOT
Davis-Bacon Prevailing Wage Rates (Section 1606) - Prevailing wage rate requirements apply to all ARRA-funded construction projects.
To ensure that all bidders using the City's Web Site are kept up to date on any addendums, changes, or informational notices; please send an e-mail to Tim Jackson indicating which bid was downloaded. Failure to complete this important step may render your bid as non-responsive.
Wednesday, October 21, 2009 Pre-Construction Meeting at 2 p.m.
Thursday, October 29, 2009 Bid Opening at 2 p.m.
Thursday, November 19, 2009 Award Date
December 3, 2009 NCDOT Concurrence of Award
February 2010 Pre-Construction Meeting
March 2010 Begin Work
June 2010 Work Complete