2015 Trenchless Pipe Repair (SD-2015-02)​

Project Manager

Dana P Hornkohl, PE
Phone: 919-560-4326, ext. *30246

Project Status

This construction contract is complete.  Prism Contractors and Engineers, Inc. performed the work under this contract.

Key Project Dates

  • Notice to Proceed: November 30, 2015
  • Final Completion: July 3, 2017

Project Description

The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete stabilization of storm drainage pipe joints by means of void filling and soil stabilization using a polyurethane system as well as various trenchless pipe repairs throughout the city.

Completed Project Sites:

  • 501 Washington Street
  • Falconbridge Road Trenchless Pipe Repair
  • Hillandale Golf Course Hole No. 1 Trenchless Pipe Repair
  • Hillandale Golf Course Hole No. 2 Trenchless Pipe Repair
  • Hillandale Golf Course Hole No. 3 Trenchless Pipe Repair
  • Hillandale Golf Course Hole No. 6 Trenchless Pipe Repair
  • Hillandale Golf Course Hole No. 18 Trenchless Pipe Repair
  • Liggett Street Pipe Repair
  • Minerva Avenue Trenchless Pipe Repair
  • North Mangum Street Trenchless Pipe Repair
  • Piney Woods Park (Ballfield) Trenchless Pipe Repair
  • Third Fork Creek Trail (Garrett Road Park)