Project Manager
Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246
(Updated March 30, 2017)
Project Status
Primary construction began on March 20, 2017 and was complete as of September 5, 2017. The work was completed ahead of schedule and the Third Fork Creek Trail is open to the public. Additional woody plants were installed in January 2018. A final set of plantings will occur after the last frost in the spring of 2018 to help stabilize the stream restoration.
Key Project Dates
- Initial Advertisement: June 20, 2016
- Initial Bid Opening: July 21, 2016
- Re-Advertisement: August 29, 2016
- Bid Opening: October 12, 2016
- Notice to Proceed: March 20, 2017
- Final Completion: October 5, 2017
PROJECT Description
The project included the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the stream restoration of Third Fork Creek and new trail boardwalk between Martin Luther King, Jr. Parkway and Cardinal Drive. This work was done to protect water quality in the creek and to improve sections of the trail to make them less susceptible to damaging floods and sediment.
Video - Long Version
Video - Short Version
Service request:
Click or call 919-560-1200