ST-264 Fayetteville Road Improvements

Project Manager


Clint Blackburn
Phone: 919-560-4326, ext. 30245

Project Description


The City is moving towards construction of project ST-264, Fayetteville Road Improvements.
The project has been updated to incorporate the former ST-254 Fayetteville/Buxton/Riddle Realignment Project, in order to more effectively utilize the City's resources and provide a more coordinated and less disruptive construction process.  

The Fayetteville Road Improvements Project will consist of widening and enhancing Fayetteville Road from Barbee Road to Cornwallis Road.  The Fayetteville/Buxton/Riddle Road Realignment Project consists of converting the junction of Buxton and Riddle Roads to a traditional intersection.  We are excited about this work and hope it will provide a welcomed improvement to the neighborhood and the traveling community. 

​Project Schedule


The anticipated completion of this project is currently November 2021.  This is an estimated date of completion, since the weather conditions impact the project schedule.

Project Status


Paving of the final asphalt surface is scheduled to begin on November 17, 2021 and continue through 11-23-2021, contingent upon the weather.  Expect delays during the hours of 9:00 AM to 4:00 PM. Fayetteville Road will remain open, but motorists are encouraged to use alternate routes if possible.

Once the paving is complete and the pavement markings are in place this section will be fully reopened to traffic.  Additional work will continue on the shoulders and occasion lane closures may still be required.  Sunday work has been permitted through November 20, 2021 between the hours of 11:00am to 4:00pm.  The contractor is required to notify all residents, businesses and churches within the limits of that work.

Advertisement Info.

5/28/2018: This project is currently available for bid as described in documents at right.

6/22/2018: Due to a lack of participation at the pre-bid meeting on June 19, this project is hereby re-advertised as of this date as described in documents at right.

7/12/2018:  Please note the addition of the Pre-Bid meeting minutes at right, along with the attendance sheet.  The attendees listed are the only prime contractors from whom the City will accept a bid.

7/24/2018: Please note the addition of Addendum 1 at right. Note also that the bid opening date has been extended to August 14, 2018.

8/8/2018: Please note the addition of Addendum 2 at right.

8/17/2018: Please note the addition of Addendum 3 at right. The project is hereby re-advertised as of this date as described in documents at right.

9/11/2018: Please note the addition of Addenda 4-6 at right. Bid opening is postponed until 3:00 PM on September 21, 2018, due to inclement weather.

KEY DATES

  • Contract Advertisement:  Friday, August 17, 2018
  • Pre-Bid Meeting:  Tuesday, September 4, 2019
  • Bid Opening:  Friday, September 21, 2018