Markham Avenue, Mangum Street, Roxboro Street Medians (ST-276)

Project Manager


Kitty M. Thomas, EI
Email
Phone: 919-560-4326, ext. 30218

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the construction of medians and other related sidewalk and roadway improvements at the intersection of Markham Avenue, Mangum Street and Roxboro Street/

Project Schedule


  • Advertisement (Current bid attempt): May 5, 2017 
  • Pre-Bid Meeting (Current bid attempt): May 25, 2017
  • Bid Opening (Current bid attempt) :  June 14, 2017
  • Construction Started: September 20, 2017
  • Anticipated Construction Completion: October 2017

Project Status


This project is in the construction phase. Work is underway. Detours are now in place from 9 a.m. to 4 p.m., Monday through Friday. A truck detour is also in effect.