This construction contract is complete.  White Oak Construction Corporation of N. C. performed the work under this contract.

Key Project Dates


  • Notice to Proceed: December 1, 2017
  • Final Completion: May 9, 2018

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.

Completed Project Sites

  • Elmira Avenue Park Drainage Structure Access
  • Winburn Avenue Pipe Replacement
  • Unity Village Park Pipe Replacement
Similar Contract: SD-2013-01