Project Manager
Yi Wang, PE
Phone: 919-560-4326, ext. 30244
Project Status
This construction contract is complete. White Oak Construction Corporation of N. C. performed the work under this contract.
Key Project Dates
- Notice to Proceed: December 1, 2017
- Final Completion: May 9, 2018
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.
Completed Project Sites
- Elmira Avenue Park Drainage Structure Access
- Winburn Avenue Pipe Replacement
- Unity Village Park Pipe Replacement
Service request:
Click or call 919-560-1200