2018 SCM Renovation and Rehabilitation (SWDR-2018-01)

Project Manager

Shea S. Bolick, PE, PLS, CFM
Phone: 919-560-4326, ext. 30270

Project Status

Notice to proceed was given and project work commenced on May 1, 2018.  The contractor (Backwater Environmental) worked diligently performing improvements on stormwater control measures in the Stonehill Estates and Ravenstone residential subdivisions, as well as at a Public Works salt dome facility.  Work was substantially complete as of October 15, 2018, with final completion August 30, 2019.  All SCMs have been turned over to their respective owners for future maintenance.  The original project completion date was October 28, 2018, however this date will be adjusted due to several mitigating factors encountered during the contract.  The completed SCMs will be further inspected/assessed prior to the end of the contract correction period, October 15, 2019, and any deficient items noted due to the contractor’s work will be corrected.

Key Project Dates

  • Initial Advertisement:  December 20, 2017
  • Pre-Bid Conference:  January 10, 2018
  • Re-Advertisement:  January 29, 2018
  • Bid Opening:  February 12, 2018 at 2:00 PM
  • Notice to Proceed:  May 1, 2018
  • Work Commencement:  May 1, 2018
  • Substantial Completion: October 15, 2018

Project Description

The project involves the furnishing of all materials, labor, equipment, tools, etc., unless otherwise specified, for renovation and rehabilitation activities performed on various stormwater control measures (SCMs) at various site locations throughout the City of Durham.