This project involves the design of sidewalks on one side of Raynor Street from N. Miami to Hardee Street. Total length is 0.3 miles. The budget for the project is $364,435 The project vicinity is shown to the right under Project Information. The improvements include new sidewalks and accessible ramps.
Project Schedule
Design Completed: November 2019
Anticipated Right-of-Way Completion: July 2022
Anticipated Bid Advertisement: December 2022
Anticipated Construction Start: May 2023
Anticipated Construction Completion: August 2023
Project Status
Ramey Kemp and Associates of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began data collection in February 2018 and currently are in right-of-way acquisition phase of the project.
The goal of the project is to improve pedestrian accommodations and the proposed improvements include curbs and gutters, ramps, and sidewalks.
Service request:
Click or call 919-560-1200