PROJECT SCHEDULE
- Design Completed: November 2019
- Anticipated Right-of-Way Completion: July 2022
- Anticipated Bid Advertisement: December 2022
- Anticipated Construction Start: May 2023
- Anticipated Construction Completion: August 2023
PROJECT STATUS
Ramey Kemp and Associates of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders. They began data collection in February 2018 and currently are in right-of-way acquisition phase of the project.
The goal of the project is to improve pedestrian accommodations and the proposed improvements include curbs and gutters, ramps, and sidewalks.