Design Services for North Duke Street Sidewalk  (SW-50D)

Project Manager

David Cates

Phone: 919-427-9370

PROJECT DESCRIPTION

This project involves the design of sidewalks on east side of N. Duke Street from Murray Ave to N. Roxboro Road. Total length is 1.8 miles.   The design budget for the project is $436,698.91.

The project vicinity map is shown to the right under Project Information. The improvements include new sidewalks, crosswalk improvements, and accessible ramps.


PROJECT SCHEDULE

  • Anticipated Design Completion:  February 2021
  • Anticipated Right-of-Way Completion:  November 2022
  • Anticipated Bid Advertisement:   April 2023 
  • Anticipated Construction Start:  September 2023
  • Anticipated Construction Completion:  November 2024

Project Status

Kimley-Horn and Associates of Raleigh, NC has been hired as the design firm to prepare plans, obtain permits, and hold informational meetings with stakeholders.  They began data collection in February 2018. Currently the project is in the right-of-way acquisition phase of the project.

The City of Durham Public Works Department prepared designs for pedestrian facilities along North Duke Street from West Murray Avenue to North Roxboro Street, and City staff solicited community input during the design process with two community input meetings.

The goal of the project is to improve pedestrian accommodations with proposed improvements include sidewalk, curb ramps, pedestrian crossings, and associated pavement markings. 

For additional information about the project, contact Todd Ireland, PE with Kimley-Horn and Associates, Inc. at (919) 682-3583 or [email protected]; or Neil Allen, with the City’s Public Works Department at (919) 471-3581 or [email protected]. Persons who require assistance to attend the meeting should call (919) 560‐4197 or email [email protected] no later than 48 hours before the event.