Project Manager
Dana P Hornkohl, PE
Phone: 919-560-4326, ext. *30246
Project Status
This construction contract is complete. Prism Contractors, Inc. performed the work under this contract.
Key Project Dates
- Notice to Proceed: November 1, 2018
- Final Completion: July 27, 2020
Project Description
The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of cured-in-place pipe (CIPP) lining of existing storm drainage pipes throughout the City of Durham.
Completed Project Sites
- Beechwood Cemetery
- Durham Area Transit Authority
- Hillandale Golf Course Hole No. 3A
- Hillandale Golf Course Hole No. 4
- Hillandale Golf Course Hole No. 13
- Stokes Street
- Stuart Drive
- Technology Drive
- Travis Circle Sinnott Circle
- Wrightwood Avenue