2018 Unpaved Roads Study (ST-292)

Project Manager


Ed Venable
Phone: 919-560-4326, ext. 30233

Project Description


This is a Request for Qualifications from engineering firms to provide professional engineering services. The selected firm will update the City’s current Unpaved Road Study, incorporating the information into a new asset management plan for these unpaved roads, and present the information to City Council.  

Project Schedule


  • Advertisement: April 16, 2018
  • Pre-Submittal Meeting: May 2, 2018
  • Last Date for Receipt of Proposals: May 16, 2018
  • Conclude Shortlisting: June 1, 2018
  • Conclude Presentations: June 22, 2018
  • Conclude Contract Negotiations: July 13, 2018
  • City Council Award: September 4, 2018
  • Contract Start Date: October 8, 2018
  • Anticipated Contract Completion: April 2019

Project Status


The contract was approved by City Council on September 4, 2018. SEPI will begin work on the study on October 8, 2018.