PROJECT MANAGER
Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246
Project Status
This construction contract is complete. UMA, Geotechnical Construction, Inc. performed the work under this contract.
Key Project Dates
- Notice to Proceed: July 31, 2018
- Final Completion: August 30, 2018
Project Description
The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete stabilization of the Carpenter Fletcher Road culvert by means of void filling and soil stabilization using a high density polyurethane system.
Similar Contracts: SD-2015-01 and SD-2012-03
Service request:
Click or call 919-560-1200