West Club Blvd. Corridor Utility Rehabilitation

Project Facts

  • Approximately 12,000 linear feet of water mains will be replaced within West Club Boulevard, 9th Street, Carolina Avenue, Oakland Avenue, Oval Drive, and Englewood Avenue. The project may also include storm drainage rehabilitation and sanitary sewer main rehabilitation following field investigations.
  • The field investigation and preliminary engineering were completed in the summer of 2019.
  • Final design is underway and expected to be complete in the winter of 2021.
  • Construction is expected to begin in early 2022.
  • Stay up to date on this project and other Water Management projects by subscribing to City news flashes here.

Project Updates

  • Ongoing
    • West Club Boulevard Corridor utility rehabilitation.
    • The project is obtaining needed easements and permits prior to construction.
  • May 2022 – July 2022
    • Hillandale Road Waterline Replacement Project

      The City of Durham is starting design of a project that will replace approximately 500 linear feet of water main alongside Hillandale Road. The map below shows the proposed project area. The existing two-inch diameter waterline is undersized and replacement is necessary to improved reliability of utility service. As a part of the project the existing two-inch diameter waterline will be replaced with a new 8-inch water main. The intent is to combine construction of this project with the larger West Club Blvd. Corridor Utility Rehabilitation project.Map of Hillandale Road Waterline Replacement Project Area Opens in new windowThe first steps of the design phase will be an initial field investigation which is expected to begin in May 2022.  The investigation will include land survey. The work will cause minimal disturbance.

  • October 2021
    • Dewberry Engineers, Inc. and the City of Durham updated residents on the project status during the WHHNA Annual meeting. The following presentation is from that meeting.
    • October 2021 Project Update
  • March – April 2021
    • Surveyors with Dewberry Engineers Inc. will conduct additional survey field work. The work will take approximately one week. Work will be done primarily in the public right-of-way, but access to a few backyards will be required to survey the location of existing sanitary sewer and stormwater facilities. The City will notify property owners regarding access to their backyards as needed. Contractors doing the survey activities will be properly identified.
    • CH Engineering, PLLC will conduct a subsurface utility investigation to identify the depth of utilities at four locations in the project area. The work will take approximately 2 days. Work will be done in the public right-of-way. Minor traffic disruptions are anticipated and residents are asked to watch for traffic control and workers in the street.
  • July - August, 2020
    • Falcon Engineering, Inc. will begin additional geotechnical investigations in the project area. The geotechnical borings will be located in the pavement of West Club Blvd, Oakland Ave., Oval Dr., Carolina Ave.,9th St., and Englewood Dr. 
    • Hydrostructures, LLC will begin additional sanitary sewer assessments to determine conditions of pipes and manholes. The additional sanitary sewer assessments will be located in in the rights-of-way of Hillandale Rd., West Club Blvd., Alabama Ave., Virginia Ave., Wilson St., Oakland Ave., Woodrow St., Englewood Ave., Lawndale Ave., W Knox St., Iredell St., #3 Alley, and Green St.
  • October 2019
  • August - September, 2019
    • Preliminary field work has wrapped up. Dewberry Engineers is in the final stages of preparing a draft preliminary engineering report. The draft report will be submitted for DWM review in September 2019. Over the past year, DWM has assessed the following items in the project area:
      • The valves and hydrants for 12,000 linear feet of water main
      • 11,000 linear feet of sanitary sewer main and manholes
      • 5,000 linear feet of storm sewer pipe
      • Tree health
      • Depth of rock and soil types
      • Pavement condition
      • Crosswalks and curb ramps
    • Design is anticipated to begin in early-2020 and construction is anticipated to begin in late-2020.
  • Week of April 22, 2019:
    • Falcon Engineering, Inc. will begin geotechnical investigations in the project area. The geotechnical borings will be located in the pavement of West Club Blvd, Oakland Ave., Carolina Ave., and 9th St. CH Engineering, PLLC will complete a Level A subsurface utility investigation on Englewood Ave. between Iredell St. and Broad St. Field personnel will work within the existing public right-of-way, wear safety vests and carry identification.
  • Week of October 8, 2018:
    • CH Engineering, PLLC will begin a subsurface utility exploration of the project area to identify and locate existing underground utilities. Temporary, non-toxic paint of various colors will be used on the ground, pavement, and sidewalks to mark the location of buried utilities throughout the project area. The paint will wash away in several weeks. Minor traffic disruptions are anticipated and residents are asked to watch for traffic control and workers in street.
  • Week of October 1, 2018:
    • Suez-Utility Service Company, Inc. will be assessing water valves and auditing fire hydrants within the project area. Loss of water service or water pressure is unlikely during the testing; however, some discoloration was water may occur. Minor traffic disruptions are anticipated and residents are asked to watch for traffic control and workers in street.
  • September – October 2018:
    • Surveyors with Dewberry Engineers Inc. will be completing a topographic survey of the area. Work will be done primarily in the public right-of-way but may also require access to front yards to survey locations of water meters, sewer cleanouts and trees. Contractors doing the survey activities will be properly identified.
  • Week of September 3 or September 9, 2018:
    • Surveyors with Dewberry Engineers Inc. will begin a topographic survey of the area. Work will be done primarily in the public right-of-way but may also require access to front yards to survey locations of water meters, sewer cleanouts and trees. Contractors doing the survey activities will be properly identified.
  • Week of August 27 or September 3, 2018:
    • Hydrostructures, LLC will begin sanitary and storm sewer assessments to determine conditions of pipes, manholes, and drains.
  • Week of August 27, 2018:
    • Arborists with Bartlett Tree Experts will begin surveying and assessing the health of trees.
  • Week of August 13, 2018:
    • Initial field investigation work will soon begin in the project area. Starting the week of August 13, residents will receive notification via door hangers outlining the project and the work to be completed in their neighborhood.

Contact Information

  • City of Durham Water Management:
    Lisa Mitchell
    Email
    919-560-4381, ext. 35568
  • Dewberry Engineering Inc.:
    Beth Steffens, PE
    Email
    984-232-6795
West Club Utility Rehab Project Area