Project Manager
Greg Smith, PE
Phone: 919-560-4326, ext. 30255
Project Status
This construction services contract is complete. FSC II, LLC performed the work under this contract.
Key Project Dates
- Notice to Proceed: November 4, 2019
- Final Completion: June 11, 2020
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of the repairs of stormwater drainage infrastructure systems at various project site locations throughout the City of Durham.
Completed Project Sites
- Bacon Street
- East Lawson Street
- Elm Street and Taylor Street
- Horton Road
- Mallard Avenue
- South Roxboro Street (2100 block)
- South Roxboro Street (5400 block)
- West Club Boulevard (300 block)
- West Club Boulevard (400 block)
- Woodcroft Parkway
Service request:
Click or call 919-560-1200