ST-299 Asphalt Rejuvenation 2019

Project Manager


Clint Blackburn
Phone: 919-560-4326, ext. 30245

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation of streets. 

This project will be applying asphalt rejuvenating oils to various streets within Durham. 

Project Schedule


  • Advertisement:  April 5, 2019 
  • Pre-Bid Meeting: April 12, 2019 at 10:00 AM
  • Bid Opening:  April 19, 2019 at 10:00 AM
  • Bid Opening:  April 22, 2019 at 2:00 PM
  • City Council Approval: June 3, 2019
  • Anticipated Construction Start: July 1, 2019
  • Anticipated Construction Completion:  October 2019

Project Status


This project is currently being advertised. Addendum 2 is posted.  The bid opening has been changed to April 22 at 2:00 PM.