Project Manager
Antwon Williams, PE
Phone: 919-560-4326, ext. 30246
Project Status
This services contract is complete. Zulu Marine Services, Inc. performed the work under this contract.
Key Project Dates
- Notice to Proceed: May 13, 2020
- Final Completion: June 8, 2020
Project Description
The Project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the removal of debris along four reaches of streams within the City of Durham.
Completed project sites
- DSR 37-01-18-5038-160, Ellerbe and South Ellerbe Creeks
- DSR 37-01-18-5038-161, Northeast Creek Tributary C
- DSR 37-01-18-5038-194, Northeast Creek Tributary C
- DSR 37-01-18-5038-195, Third Fork Creek Tributary E
Service request:
Click or call 919-560-1200