This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation, repair, and repaving of various streets throughout the City of Durham.
For information on pavement preservation techniques, see the links on the right.
Project Schedule
Advertisement: September 26, 2019
Pre-Bid Meeting: October 10, 2019 at 2:00 PM
Bid Opening: October 25, 2019 at 10:00 AM
City Council Approval:December 17, 2019
Anticipated Construction Start: April 1, 2020
Anticipated Construction Completion: July 2020
Project Status
Additional streets have been added to ST-302. A portion of the Grove Park Neighborhood and streets in the Kirkwood Area. The vicinity maps are on the right side of the page.
Service request:
Click or call 919-560-1200