Project Manager
Greg Smith, PE
Phone: 919-560-4326, ext. *30255
Project Status
This construction services contract is complete. Visco Transportation Corporation initially performed the work under this contract prior to termination for convenience, effective October 20, 2020. Carolina Civilworks, Inc. performed the remaining contract work.
Key Project Dates
- Notice to Proceed: May 1, 2020
- Notice of Termination: October 13 2020
- Substantial Completion: March 22, 2021
- Final Completion: April 2021
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete replacement of the existing storm drainage culvert where Alpine Road intersects Tributary C of Third Fork Creek.
Service request:
Click or call 919-560-1200