PROJECT MANAGER
Antwon Williams, PE
Phone: 919-560-4326, ext. 30254
Project Status
The project is proposed to begin construction in the late 2020. Construction Drawings for the Odyssey Drive Culvert Replacement project have been approved and acquisitions of right-of-way and construction easements are underway. The construction contract was awarded to the Fred Smith Company (FSC). Currently FSC is working with private utility companies to relocate under ground communication lines. The Notice to Proceed was issued for February 2021. Construction was completed in November 2021.
Key Project Dates
- Advertisement: June 29, 2020
- Pre-Bid Conference: July 29, 2020
- Bid Opening: August 12, 2020
- Notice to Proceed: February 2021
- Substantial Completion: September 10, 2021
- Completion: November 12, 2021
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete replacement of the existing storm drainage culvert where Odyssey Drive intersects the northern prong of Northeast Creek.
Service request:
Click or call 919-560-1200