ST-286 Petition Streets 2021

Project Manager


Ana E. Jaramillo, PE
Phone: 919-560-4326, ext. 30233

Project Description


The Project involves the furnishing of all materials, labor, equipment, tools, et cetera, unless otherwise specified, for the complete installation of new pavement on Amber Place, Brunson Street, Chalmers Street, Lang Street, Leonard Drive, Omah Street, and Turner Street.

PROJECT SCHEDULE

The following schedule is estimated and may change.
  • Re-Advertisement: October 14, 2020
  • Pre-Bid Meeting: October 21, 2020
  • Bid Opening: October 28, 2020

Project Status


This project started construction in September 2021. The contractor for this project is Carolina Sunrock (CSR) and it will be inspected by Johnson, Mirmiran & Thompson, Inc. (JMT). Below is the contact information for them if you have any construction related questions:

CSR - Superintendent - Jarred Burns: [email protected] (984) 789-2321
CSR - Project Manager - Matt McCullough: [email protected] (919) 909-4342

JMT - Project Manager - Philip Townsend, PE: [email protected] (984) 269-4909

Construction on Chalmers Street section continues.

Construction activities for Leonard Drive and Turner Street sections are scheduled to start mid to late April, 2022 and end on October, 2022.