Project Manager
Ana E. Jaramillo, PE
Phone: 919-560-4326, ext. 30233
Project Description
The Project involves the furnishing of all materials, labor, equipment, tools, et cetera, unless otherwise specified, for the complete installation of new pavement on Amber Place, Brunson Street, Chalmers Street, Lang Street, Leonard Drive, Omah Street, and Turner Street.
PROJECT SCHEDULE
The following schedule is estimated and may change.
- Re-Advertisement: October 14, 2020
- Pre-Bid Meeting: October 21, 2020
- Bid Opening: October 28, 2020
Project Status
This project started construction in September 2021. The contractor for this project is Carolina Sunrock (CSR) and it will be inspected by Johnson, Mirmiran & Thompson, Inc. (JMT). Below is the contact information for them if you have any construction related questions:
CSR - Superintendent - Jarred Burns: [email protected] (984) 789-2321
CSR - Project Manager - Matt McCullough: [email protected] (919) 909-4342
JMT - Project Manager - Philip Townsend, PE: [email protected] (984) 269-4909
Construction activities on Chalmers Street section continues and are expected to end in late August.
Construction activities on Leonard Drive and Turner Street sections started late April, 2022 and are expected to end in late October, 2022.
Construction Activities for Amber Place section is scheduled to start on early August, 2022 and end late December 2022.
Service request:
Click or call 919-560-1200