ST-286 Petition Streets 2021

Project Manager

Ana E. Jaramillo, PE

Phone: 919-560-4326, ext. 30233


Project Description

The Project involves the furnishing of all materials, labor, equipment, tools, et cetera, unless otherwise specified, for the complete installation of new pavement on Amber Place, Brunson Street, Chalmers Street, Lang Street, Leonard Drive, Omah Street, and Turner Street. 


PROJECT Schedule

The following schedule is estimated and may change.

  • Re-Advertisement: October 14, 2020
  • Pre-Bid Meeting: October 21, 2020
  • Bid Opening: October 28, 2020


Project Status

This project started construction in September 2021. The contractor for this project is Carolina Sunrock (CSR) and it will be inspected by Johnson, Mirmiran & Thompson, Inc. (JMT). Below is the contact information for them if you have any construction related questions:

CSR - Superintendent - Jarred Burns: [email protected] (984) 789-2321
CSR - Project Manager - Matt McCullough: [email protected] (919) 909-4342

JMT - Project Manager - Philip Townsend, PE: [email protected] (984) 269-4909

Omah Street, Chalmers Street, Leonard Drive, Turner Street, Amber Place and Lang Street sections have been already paved.

Construction activities for Brunson Street section started on late January 2023 and are expected to end on late October 2023.