This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the preservation, repair, and repaving of various streets throughout the City of Durham.
For information on pavement preservation techniques, see the links on the right.
Project Schedule
Advertisement: September 09, 2020
Pre-Bid Meeting: September 23, 2020 at 10:00 AM
Bid Opening: October 09, 2020 at 10:00 AM
City Council Approval:December 06, 2020
Anticipated Construction Start: April 1, 2021
Anticipated Construction Completion: October 2021
Project Status
This project will be patching and repaving various streets in Durham. The vicinity maps for the project are on the right banner of this page. Fred Smith Company has begun work in the Erwinwood Neighborhood and are scheduled to start working in the Hope Valley North Neighborhood on April 21.
Service request:
Click or call 919-560-1200