PROJECT DESCRIPTION
This project includes repaving and improving drainage conditions along Durham's trails listed below:.

  1. Ellerbe Creek Trail
  2. Rock Quarry Spur/Vietnam Veterans Memorial Trail
  3. American Tobacco Trail - Phase D
  4. Riddle Road Spur Trail
  5. West Ellerbe Creek Trail
  6. Warren Creek Trail
  7. Rocky Creek Greenway
  8. South Ellerbe Creek Trail
  9. Renaissance Parkway Sidepath
  10. Sandy Creek Trail
  11. New Hope Creek Trail

PROJECT SCHEDULE
The following schedule is estimated and may change.

  • Advertisement:  April 22, 2021
  • Pre-Bid Meeting: Wednesday, May 5, 2021, @ 11;00 AM. 
  • Bid Opening: Friday, May 21, 2021 @ 1;00 PM. 
  • Second Bid opening: June 24, 2021 @ 1:00 PM. 
  • Construction Start Date: March 21, 2022
  • Anticipated Contract Completion:  Spring 2023. 

PROJECT Status
The contract has been awarded to Browe Construction. 

Construction is currently underway.