Project Manager
Carol Teabo, EIT
Phone: 919-560-4326, ext. *30389
Project Status
This services contract was advertised on June 28, 2021. A Pre-Submittal Conference (minutes) was held on July 27, 2021. Addendum No. 1 was issued on July 13, 2021. Addendum No. 2 was issued on July 27, 2021. Addendum No. 3 was issued on August 17, 2021.
A Notice of Award - Notice to Proceed has been issued to Hydrostructures, PA on January 4, 2022.
Contract Amendment No. 1 (Fiscal Year 2023) Notice to Proceed has been issued on January 3, 2023.
Contract Amendment No. 2 (Fiscal Year 2024) has been submitted for review.
Key Project Dates
- Advertisement: June 28, 2021
- Pre-Submittal Conference: July 27, 2021 (minutes)
- Submittal Deadline: September 1, 2021, 11 am
- Notice to Proceed: January 2022
Project Description
The project includes the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for stormwater structure (basin) inspections throughout the City of Durham as well as the complete inspection of portions of the Municipal Separate Storm Sewer System (MS4) for specified site locations throughout the City of Durham. Inspections of the MS4 shall include location and verification of system components, inspections to locate possible illicit discharges into the system, and general inspections of system components to document condition. It is the City’s intent that this contract shall be issued for a period of one year, and if the work proceeds successfully, the contract could be renewed annually for a total of five years.
Similar Contracts: SD-2019-06 & SD-2019-07, SD-2017-03, SD-2014-01, and SD-2012-04.
Service request:
Click or call 919-560-1200