2021 Stormwater Infrastructure Repairs (SD-2021-05)​

Project Manager

Phone: 919-475-2287

Assistant: Carol Teabo, EIT
Phone: 919-907-9572

Project Status


The project is proposed to begin construction in early 2022. Construction easements are ongoing. The construction contract was awarded to Pipeline Utilities, Inc. The Contract Notice to Proceed was issued on January 4, 2022. Edison Johnson Recreation Center (COP-127) was issued a Notice to Proceed for April 4, 2022.

Key Project Dates


  • Bid Posting/Advertisement: Thursday, June 17, 2021
  • Pre-Bid Conference: 10:00 AM, Wednesday, July 7, 2021
  • Bid Opening: 10:00 AM, Thursday, August 19, 2021
  • Notice to Proceed: January 2022
  • Final Completion: November 2023 (anticipated)

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.

Project Sites


  • Edison Johnson Recreation Center Stormwater Pipe Repairs (COP-127)
  • North Buchanan Boulevard Storm Replacement (PDAP-046)
  • Winton Road Pipe Network Replacement (PDAP-041)
  • Fairview Street Storm Replacement (PDAP-063)
  • Stuart Drive Pipe Network Replacement (PDAP-069)
  • Kamis Street Drainage Plan (PDAP-079)
  • West Club Blvd. Culvert Replacement (ROW-192)

West Club Blvd. "Before" Video and Photos