ST-316 Bridge Repairs 2023

Project Manager


James Steinberger
Phone: 919-560-4326, ext. 30266

PROJECT DESCRIPTION


This project involves:

  • Repairing the various bridges in Durham that have degraded. Repairs include everything from guard rail adjustments to superstructure repair and heat treatment of steel beams. The list below details the location of each bridge to be repaired.
1.) Bridge #310231 – Bellevue Ave. over Ellerbe Creek
2.) Bridge #310240 – Shoccoree Dr. over Ellerbe Creek
3.) Bridge #310243 – Liberty St. over Goose Creek
4.) Bridge #310246 – Pettigrew St. over Campus Drive
5.) Bridge #310280 – Ramseur St. over S. Roxboro Street
6.) Bridge #310448 – North Point Dr. over Ellerbe Creek
7.) Bridge #310579 – MLK Jr. Pkwy. over Third Fork Creek
8.) Bridge #310626 – American Tobacco Trail over I-40

Project Schedule


  • Advertisement: February 23, 2022.
  • Pre-Bid Meeting: March 9, 2022 @ 11 A.M.
  • Bid Opening:  Tuesday, March 29, 2022 @ 1:00 PM (Virtual Meeting).
  • Second Advertisement: April 8, 2022.
  • Pre-Bid Meeting: April 22, 2022 @ 1 PM (Virtual Meeting). 
  • Bid Opening:  Tuesday, May 10, 2022 @ 1:00 PM (Virtual Meeting).
  • Anticipated Construction Start: Late Summer of 2022.
  • Anticipated Construction Completion: Early 2023. 

Project Status


The following are the bid results for the ST-316 Bridge Repairs 2022 project:

Fred Smith Company - $1,528,927.42

Engineer's Estimate - $395,377.20