Project Manager
Mike Boyd, MSM
Phone: (984) 227-4486
Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete inspection of asphalt, sidewalk, curb and gutter (concrete & granite), driveway aprons, curb ramps, brick paver removal and installation at various locations within the City of Durham where Water & Sewer repairs and new installations were performed.
Project Schedule
- Advertisement: February 4, 2022
- Pre-Proposal Meeting: Friday, February 18, 2022 at 10:00 AM (via ZOOM)
https://us02web.zoom.us/j/89966520357?pwd=YmpPVzlLOEkveWlod2ZKSUJRWFZjdz09
Meeting ID: 899 6652 0357
Passcode: Beb6Ca
- Bid Proposal Due Date: Monday, March 7, 2022 by 2:00 PM
- Anticipated Construction Start: June, 2022
- Anticipated Construction Completion: August, 2023
Project Status
Awarded to Horvath & Associates, construction and inspection services are in motion.
Addendum #1 posted on 3/3/22
Service request:
Click or call 919-560-1200