ST-322 Maryland Ave. Bridge Removal

Project Manager


James Steinberger

Phone: 919-560-4326, ext. 30266


PROJECT DESCRIPTION

This project consists of furnishing all labor, equipment, and materials to remove the existing Bridge No. 310233, grading of existing channel side slopes, and installation stream bank restoration devices and erosion control measures as directed in the contract documents. Work also includes repairs to adjacent storm sewer networks and replacement of existing aerial utility support piers and installation of utility encasement pipes.

Project Schedule

  • Advertisement: October 31, 2022
  • Pre-Bid Meeting: Thursday, November 17, 2022 at 2:00 PM (Virtual Meeting)
  • Bid Opening: Wednesday, December 14, 2022 at 2:00 PM (In-Person)
  • Anticipated Construction Start:  May 2023
  •  Anticipated Construction Completion:  September 2023

Project Status

This project has been awarded to McQueen Construction, Inc.