PROJECT DESCRIPTION


This project consists of furnishing all labor, equipment, and materials to remove the existing Bridge No. 310233, grading of existing channel side slopes, and installation stream bank restoration devices and erosion control measures as directed in the contract documents. Work also includes repairs to adjacent storm sewer networks and replacement of existing aerial utility support piers and installation of utility encasement pipes.

Project Schedule


  • Advertisement: April 11, 2022.
  • Pre-Bid Meeting: April 22, 2022 @ 2:00 PM (Virtual Meeting).
  • Bid Opening:  Tuesday, May 10, 2022 @ 2:00 PM (Virtual Meeting).
  • Anticipated Construction Start: Late Summer of 2022.
  • Anticipated Construction Completion: End of 2022. 

Project Status

The following are the bid results for the ST-322 Maryland Ave. Bridge Removal project:

Fred Smith Company - $476,269.41
Roadworks Construction Company, LLC - $616,984.29
Engineer's Estimate - $348,160.12