2022 Stormwater Infrastructure Repairs (SD-2022-02)​

PROJECT MANAGER

Lead: Greg Smith, PE
Phone: 919-560-4326, ext. 30255

Phone: 919-560-4326, ext. 30267

Project Status

This project web page was updated on August 10, 2023.

Roadworks Construction Company is the contractor for this contract. They began work in June of 2023 and have completed one (1) project site. See Project Sites below.

If you are interested in hearing from us directly regarding future bid opportunities, please email Public Works Stormwater Infrastructure Group and request to be added to our interested bidders list.

Key Project Dates

  • Advertisement: October 21, 2022
  • Pre-Bid Conference: 3:00 p.m., November 15, 2022
  • Bid Opening: 2:00 p.m., December 20, 2022
  • Notice to Proceed: May 4, 2023
  • Construction Began: June 2023
  • Construction Completion: September 2024 (anticipated)

Project Description

The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.

Project Sites

  • 1800, 1804, and 1808 Glendale Avenue (PDAP-093) - IN PROGRESS
  • Glendale Avenue (1507) Stormwater Repairs and Improvements (ROW-184)
  • Duke Park Drainage System Repairs (COP-027)
  • Dallas Street American Tobacco Trail Connection (COP-121)
  • 5026 & 5102 Bridgewood Drive (PDAP-067)
  • Seaton Road Drainage Improvements (ROW-161)

COMPLETED SITES

  • Lee Street Pipe Replacement (ROW-261)