2022 Stormwater Infrastructure Repairs (SD-2022-02)​

Project Manager

Greg Smith, PE
Phone: 919-560-4326, ext. 30255


Project Status


This project web page was updated on November 28, 2022.

This City is advertising for construction bids beginning October 21, 2022 for seven (7) stormwater infrastructure repair projects.  The contract number is SD-2022-02 and the bid posting is HERE.  A pre-bid conference was be held at Durham City Hall, Public Works Conference Room 3B at 3:00 PM on November 15, 2022.  The pre-bid conference was not mandatory but attendance was encouraged.  A bid opening is scheduled for 11:00 AM on December 6, 2022, also in Conference Room 3B.  If you are interested in receiving updates on this contract, please email the project manager and you will be added to the Project Manual Holders List.

If you are interested in hearing from us directly regarding future bid opportunities, please email us as [email protected] and request to be added to our list.


Key Project Dates


  • Advertisement: October 21, 2022
  • Pre-Bid Conference: 3:00 PM, November 15, 2022
  • Bid Opening: 11:00 AM, December 6, 2022
  • Notice to Proceed: March 2023

Project Description


The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.

Project Sites


  • Duke Park Drainage System Repairs (COP-027)
  • Dallas Street American Tobacco Trail Connection (COP-121)
  • 5026 & 5102 Bridgewood Drive (PDAP-067)
  • 1800, 1804, and 1808 Glendale Avenue (PDAP-093)
  • Seaton Road Drainage Improvements (ROW-161)
  • Glendale Avenue (1507) Stormwater Repairs and Improvements (ROW-184)
  • Lee Street Pipe Replacement (ROW-261)