PROJECT MANAGER
Bayan Alzubi, EI
Phone: 919-560-4326, ext. 30296
PROJECT DESCRIPTION
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks and curb ramps at various locations throughout the city of Durham.
PROJECT SCHEDULE
- Re-advertisement: November 30, 2022
- Pre-Bid Meeting: No Pre-Bid Meeting will be held for this re-advertisement.
- 2nd Bid Opening: Wednesday, December 7, 2022 at 10:00 AM (In-Person)
- Construction Start: March 2023
- Anticipated Construction Completion: April 2024
PROJECT STATUS
This project has been awarded to Browe Construction Company.
Sidewalks scheduled for repair
See area maps of where sidewalks improvements are scheduled.
Service request:
Click or call 919-560-1200