PROJECT MANAGER
James Steinberger
Phone: 919-560-4326, ext. 30266
PROJECT DESCRIPTION
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks and curb ramps at various locations throughout the city of Durham.
PROJECT SCHEDULE
- Re-advertisement: November 30, 2022
- Pre-Bid Meeting: No Pre-Bid Meeting will be held for this re-advertisement.
- 2nd Bid Opening: Wednesday, December 7, 2022 at 10:00 AM (In-Person)
- Notice to Proceed: Monday, March 27, 2023
- Anticipated Construction Completion: May 2024
PROJECT STATUS
Curb ramps and sidewalk repairs are underway on Downing Creek Pkwy, Bacon St, and Blackwell St.
Sidewalks scheduled for repair
See area maps of where sidewalks improvements are scheduled.
Service request:
Click or call 919-560-1200