SW-91 PW Street Maintenance Repairs 2023

ROJECT MANAGER

Mike Boyd, MSM
Phone: (984) 227-4486 

PROJECT DESCRIPTION

This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of asphalt pavement and repairs, sidewalk, curb and gutter (concrete & granite), (ADA) curb ramps, driveway apron and brick pavers at various locations within the City of Durham where Water & Sewer repairs were performed.

PROJECT SCHEDULE

The following schedule is estimated and may change.

  • Advertisement:  February 15, 2023
  • Pre-Bid Meeting:  Wednesday, March 1, 2023 at 10:00 AM (Virtually); details will be provided 24 hrs. prior to meeting.
    • Click here to join the meeting 

      Meeting ID: 274 167 021 262 
      Passcode: XpGYma 

    • Pre-Bid meeting was conducted on 3/1/2023 

  • Initial Bid Opening:  Conducted on Wednesday, March 22, 2023 at 10:00 AM; re-advertised 
  • 2nd Bid Opening:  Thursday, April 6, 2023 at 10:00 AM (In-Person) 
  • Anticipated Notice to Proceed:  June 2023
  • Construction Start:  July 2023
  • Anticipated Construction Completion:  July 2024

PROJECT STATUS

This project has been awarded to Browe Construction Company.