2023 Paces Ferry Drive Culvert Stabilization (SD-2023-07)​

PROJECT MANAGER 

Antwon Williams
Phone: 919-560-4326, ext. 30254

Project Status

The City advertised for construction bids beginning March 24, 2023. Construction is anticipated to begin in Spring 2023. 

If you are interested in hearing from us directly regarding future bid opportunities, please email us at Public Works Stormwater Infrastructure Group and request to be added to our list of interested construction bidders. 

Key Project Dates

  • Advertisement: March 24, 2023
  • Bid Opening: April 11, 2023
  • Notice to Proceed: May 2023 (Anticipated)
  • Substantial Completion: May 2023 (Anticipated) 
  • Completion: June 2023 (Anticipated)

Project Description

The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete stabilization of the Paces Ferry Drive culvert by means of void filling and soil stabilization using a high density polyurethane system.