Project Status
The City advertised for construction bids beginning March 30, 2023. A bid opening was held on April 11, 2023. One bid was received and rejected from the bid opening. A construction contract was approved by the City Manager on September 13, 2023 with UMA, Geotechnical Construction Inc. Construction will begin in November 2023.
If you are interested in hearing from us directly regarding future bid opportunities, please email us at Public Works Stormwater Infrastructure Group and request to be added to our list of interested construction bidders.
Key Project Dates
- Advertisement: March 30, 2023
- Bid Opening: April 11, 2023
- Notice to Proceed: November 8, 2023
- Substantial Completion: November 17, 2023
- Completion: November 30, 2023
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete stabilization of the Paces Ferry Drive culvert by means of void filling and soil stabilization using a high density polyurethane system.