This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of asphalt pavement and repairs, sidewalk, curb and gutter (concrete & granite), (ADA) curb ramps, driveway apron and brick pavers at various locations within the City of Durham where Water & Sewer repairs were performed.

PROJECT SCHEDULE

  • Advertisement:  November 22, 2023
  • Pre-Bid Meeting: Thursday, December 14, 2023 at 10:00 AM (Virtually)
  • Microsoft Teams Meeting 

    Join on your computer, mobile app or room device 

    Click here to join the meeting 

    Meeting ID: 277 515 768 399 
     
    Passcode: nF4wqq

  • Bid Opening:  Wednesday, January 3, 2023 at 11:00 AM (101 City Hall Plaza, Ste. 3100, 3rd fl., Durham, North Carolina


  • Second Bid Opening:  Thursday, January 11, 2024 at 10:00 AM
  • Anticipated Notice to Proceed:  April 2024
  • Construction Start:  April/May 2024
  • Anticipated Construction Completion:  May 2025

PROJECT STATUS

This project is currently being re-advertised with a Bid Opening scheduled for January 11, 2024.