2013 Sidewalk Repairs & Curb Ramps (SW-29)

Project Manager
Eric Marsh, EI
Email
Phone: 919-560-4326, ext. 30296

Project Description
This project will provide needed repairs to existing sidewalk at various locations throughout Durham. The project will install new curb ramps that are compliant with the Americans with Disabilities Act (ADA). The Project Manual for SW-29 includes bid documents, technical specifications and details. The list of sites is linked on the right of this page under Project Information

Project Schedule
  • Advertisement: November 13, 2012
  • Pre-Bid Meeting: November 28, 2012
  • EO/EA Pre-qualification Deadline: December 6, 2012
  • Bid Opening: December 13, 2012
  • Anticipated Construction Time: April-December 2013
Project Update
November 29, 2012: Pre-Bid Attendance sheet link added to the right of this page under Project Information.