Project Manager
Clint Blackburn, EI
Email
Phone: 919-560-4326, ext. 30245
Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete removal and installation of sidewalks along portions of Ash Street, Guthrie Avenue, and Buchanan Boulevard.
Project Schedule
- Advertisement: March 12, 2015
- Pre-Bid Meeting: March 18, 2015
- Deadline for Questions: March 25, 2015
- Bid Opening: April 1, 2015
- Anticipated Construction Completion: March 2016
Project Status
This project is complete. The bid opening was held on April 1, 2015. The City received 2 bids and Lanier Construction was awarded the contract.
Service request:
Click or call 919-560-1200