2015 Speed Hump Construction (ST-275)​

Project Manager
Kitty Thomas
Email
Phone: 919-560-4326, ext. 30218

Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of 12 speed humps and removal of 5 existing speed humps at various locations throughout Durham. The removal of speed humps includes but is not limited to required milling and patching, shoulder reconstruction and resurfacing of the street.

Project Schedule
  • Advertisement - February 9, 2015
  • Pre-Bid Meeting - March 25, 2015
  • Bid Opening - April 8, 2015, at 3 p.m.
  • Anticipated Completion - July 2015
Project Status
The bid opening was held on April 8, 2015. The City received two bids and Asphalt Experts Inc. was the apparent low bidder. The bids received were:
  • Turner Asphalt Inc. $155,060.20
  • Asphalt Experts Inc. $42,482 (Apparent Low Bidder)