2012 Pavement Condition Survey (ST-263)

Project Manager
Michael Hughes, PE
Email
Phone: 919-560-4326, ext. 30266

Key Project Dates
  • February 13, 2012 - Issue RFQ
  • February 22, 2012 - Pre-qualification Conference
  • March 15, 2012 - Receive Qualifications Statements
  • April, 2012 - Qualification Evaluation Committee completes evaluation
  • April/May, 2012 - Shortlist of firms provide presentations
  • June, 2012 - Contract negotiations
  • July, 2012- City Council Approval of Contract
  • August, 2012 - Notice to Proceed
  • December, 2012 - Pavement Evaluations complete
  • January, 2013 - Delivery of report, MicroPaver and Azteca software installation and training
Project Description
The project consists of a field survey of the pavement condition on all of the city streets following the ASTM Standard D6433-11 “Standard Practice for Road and Parking Lots Pavement Condition Index (PCI) Surveys,” and associated tasks as described in the “Request for Qualifications” document.

To ensure that all bidders using the Department of Public Works website are kept up to date on any addenda, changes, or information notices, email Michael Hughes indicating your intention to submit qualifications for the project.