2017 Ravenstone and Stone Hill Estates Paving Project (ST-278)

Project Manager


Kitty M. Thomas, EI
Phone: 919-560-4326, ext. 30218

Project Description


This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the repair and final paving of various streets in Ravenstone and Stone Hill Estates subdivisions as well as micro-surfacing of various streets in or near these subdivisions in the City of Durham.

Project Schedule

  • Advertisement: November 9, 2016
  • Pre-Bid Meeting: November 17, 2016 at 11 a.m.
  • Bid Opening: December 8, 2016 at 10 a.m.   *Apparent Low Bidder: Fred Smith Co.*
  • Meeting with residents of Ravenstone subdivision:  April 17, 2017 at 6 p.m. at the East Regional Library
  • Meeting with residents of Stone Hill Estates subdivision :  April 24, 2017 at 6:15 p.m. at Southern High School Media Center
  • Second meeting with residents of Stone Hill Estates subdivision:  June 5, 2017 at 7:15 p.m. at the East Regional Library
  • Construction Start in Ravenstone subdivision:  May 10, 2017
  • Anticipated Construction Start in Stone Hill Estates subdivision: July 5, 2017
  • Anticipated Construction Completion: September 2017

Project Status/Update

Construction phase underway. Final lift asphalt paving in both subdivisions have been completed. Micro-surfacing work was also completed. Final inspections and work on punch list items being worked on now.

Construction Phase Updates

  • Week of September 5: Final Inspection and Punch list preparation for Ravenstone subdivision
  • Week of September 11: Final Inspection and Punch list preparation for Stone Hill Estates subdivision
  • Week of September 18: Finish work on repair/ punch list items

*Work schedules are subject to change