2013 Routine Ditching & Pipe Replacement (SD-2013-04)

Project Manager

Dana P Hornkohl, PE
Phone: 919-560-4326, ext. 30246

Project Status

Work on this contract is underway.

Key Project Dates

  • Notice to Proceed: April 14, 2014
  • Final Completion: February 13, 2017

Project Description

The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of replacement storm drainage pipe and structures as well as grading of existing road side ditches within City of Durham rights-of-way.

Completed Project Sites

  • American Tobacco Trail Pipe Replacement No. 1
  • American Tobacco Trail Pipe Replacement No. 2
  • Campus Hills Park Outfall Channel
  • Hart Street Pipe Replacement
  • North Mangum Street Pipe Replacement
  • Rosedale Avenue Pipe Replacement
  • Watts Street at Minerva Avenue Pipe Replacement
  • Watts Street Pipe Replacement No. 2
  • Arnette Avenue Pipe Replacement