This project was funded by the American Recovery and Reinvestment Act (ARRA).
Contract SW-25 Project
2010 Sidewalk Construction and Repairs was awarded to Triangle Grading and Paving, Inc. of Burlington, N.C. on November 19, 2009, with NCDOT Concurrence of Award on December 3, 2009. The project was completed on December 15, 2009. The project involved furnishing of all materials. Installation of sidewalk and curb cut ramps at 6 locations throughout the City of Durham. The project manual, plans, addenda and other reporting information were made available on this site. The 6 locations were portions of:
- Dearborn Drive
-
Hillandale Road
-
Hillsborough Road and Markham Avenue
-
Hope Valley Road
-
Washington Street
-
University Drive
The project was completed in October 2011 and is awaiting a final audit by the Federal Highway Administration.
Service request:
Click or call 919-560-1200