2014 Speed Humps (ST-273)​

Project Manager
Clint Blackburn
Email
Phone: 919-560-4326, ext. 30245

Project Description
This project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of speed humps at various locations throughout Durham.

Project Schedule
  • Advertisement: March 3, 2014
  • Pre-Bid Meeting: March 19, 2014 at 3 p.m.
  • Bid Opening: April 2, 2014, at 2 p.m.
  • Anticipated Completion: July 2014
Project Status
All speed humps have been installed for this contract:
  • Carroll Street
  • Harvard Avenue
  • Pear Tree Lane
  • Ryan Street
  • South Adams Street
  • Trotter Ridge Road