Key Project Dates
- Project Manual Release: October 24, 2011
- Advertisement for Bids: October 24, 2011
- Pre-Bid Conference: November 7, 2011
- Addenda: November 22, 2011
- Bid Opening: December 5, 2011
- Notice to Proceed: January, 2012
- Substantial Completion: June 12 and July 10, 2012
Project Description
The project involves the furnishing of all materials, labor, equipment, tools, etc. unless otherwise specified, for the complete installation of repairs, rehabilitation, and improvements of stormwater drainage systems at various site locations throughout the City of Durham.
To ensure that all bidders using the Department of Public Works website are kept up to date on any addenda, changes, or information notices, send an email indicating your intention to prepare a bid for the project.
Project Update
The following project sites were substantially completed in the following order:
- Ninth Street
- Carolina Avenue
- Long Meadow Park
- Sherbon Drive
- Alexander Avenue
- University Drive
- Hillgrand Drive
- Alabama Avenue
- W Knox Street
- W Markham Avenue