Thank you for keeping up with progress through these two-week look ahead reports! Phase 1 of construction began on October 5, 2020. The City appreciates your ongoing patience with the work along the busy corridors associated with this project.
Planned Road / Lane Closures will occur as follows:
- Week of 10/19:
- Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.
- Week of 10/26:
- Northbound lane closure of Willard Street between Julian Carr Street and Jackson Street.
Week of October 19, 2020:
- Willard Street between Julian Carr St and Jackson St will have a northbound lane closure to accommodate waterline installation.
- Traffic control signs and markings will be used for the Willard Street northbound detour.
- Flaggers will be utilized for traffic control while work is taking place in the intersection of Willard and Julian Carr streets.
- Sidewalk traffic will be disrupted.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
Saturday – Sunday October 24-25, 2020:
- No work will take place on Saturday or Sunday.
Week of October 26, 2020:
- Willard Street between Julian Carr St and Jackson St will have a northbound lane closure to accommodate waterline installation.
- Traffic control signs and markings will be used for the Willard Street northbound detour.
- Flaggers will be utilized for traffic control while work is taking place in the intersection of Willard and Julian Carr streets.
- Sidewalk traffic will be disrupted.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
Saturday – Sunday October 31 – November 1, 2020:
- No work will take place on Saturday or Sunday.
If you have questions, please email [email protected].
(To subscribe to future updates, select the Notify Me letter icon in the Tools list on the right side of this page. This will take you to a list of all City subscription opportunities. Scroll to the top of the page; you’ll see a prompt to login or subscribe. Enter your email address or phone number, return to the News Flash section, select the letter or phone icon beside the entry for American Tobacco District Waterline Replacement Project Updates, and confirm your subscription by verifying the link sent. You can unsubscribe at any time.)