Project Updates: American Tobacco District Waterline Replacement

Posted on: July 23, 2021

[ARCHIVED] Project Update | July 23

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

July 23, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 7/26: 
    • Full closure of NC-147 Exit 12C to Duke Street for four nights (10 PM – 6 AM) beginning July 26. Detour route
    • Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
    • Lane closures and shifts in Chapel Hill Street between Gregson Street and Willard Street.
  • Week of 8/2: 
    • Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
    • Lane closures and shifts in Chapel Hill Street between Gregson Street and Willard Street.
    • Temporary closures of the Yancey / Duke and Jackson / Duke intersections on the west side of Duke Street.

Bicycle Lane and Sidewalk impacts will occur as follows:

  • Dedicated bike lanes in Chapel Hill Street between Willard and Gregson streets will be removed as part of roadway lane shifts.
  • The sidewalk on the south side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
  • The sidewalk on the west side of Duke Street between Yancey Street and Chapel Hill Street will have temporary closures to accommodate waterline installation.

Saturday – Sunday July 24-25, 2021:

  • No work will take place on Saturday or Sunday.

Week of July 26, 2021:

  • Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Durham Freeway Exit 12C to Duke Street will be closed for four nights (10 PM - 6 AM) beginning July 26th to July 29th to accommodate waterline installation.
      • One lane of northbound traffic along Duke St will be maintained during Exit 12C closure.
      • Detour Route
    • Lane shifts in Duke Street between Yancey and Chapel Hill streets using temporary pavement markings are implemented.
    • Lane shifts in the Duke Street and Chapel Hill street intersection using temporary pavement markings are implemented for intersection waterline installation.
    • Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the west side of Duke Street between Yancey Street and Chapel Hill Street will have temporary closures to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM, outside of the planned night work for four nights from 10 PM to 6 AM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Chapel Hill Street between Gregson and Willard streets using temporary pavement markings are implemented.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the south side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday July 31- August 1, 2021:

  • No work will take place on Saturday or Sunday.

Week of August 2, 2021:

  • Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Duke Street between Yancey and Chapel Hill streets using temporary pavement markings are implemented.
    • Lane shifts in the Duke Street and Chapel Hill street intersection using temporary pavement markings are implemented for intersection waterline installation.
    • Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place in the Duke / Yancey and Duke / Jackson intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the west side of Duke Street between Yancey Street and Chapel Hill Street will have temporary closures to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
    • Lane shifts in Chapel Hill Street between Gregson and Willard streets using temporary pavement markings are implemented.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • The sidewalk on the south side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday – Sunday August 7-8, 2021:

  • No work will take place on Saturday or Sunday.

If you have questions, please email [email protected].

Facebook Twitter Email

Other News in Project Updates: American Tobacco District Waterline Replacement

American Tobacco Waterline Replacement

Project Update | February 1, 2023

Posted on: February 1, 2023
American Tobacco Waterline Replacement

Project Update | March 11, 2022

Posted on: March 11, 2022
American Tobacco Waterline Replacement

Project Update | March 4, 2022

Posted on: March 4, 2022
American Tobacco Waterline Replacement

Project Update | February 25, 2022

Posted on: February 25, 2022
American Tobacco Waterline Replacement

Project Update | February 18, 2022

Posted on: February 18, 2022
American Tobacco Waterline Replacement

Project Update | February 11, 2022

Posted on: February 11, 2022
American Tobacco Waterline Replacement

Project Update | February 4, 2022

Posted on: February 4, 2022
American Tobacco Waterline Replacement

Project Update | January 28, 2022

Posted on: January 28, 2022
American Tobacco Waterline Replacement

Project Update | January 21, 2022

Posted on: January 21, 2022
American Tobacco Waterline Replacement

Project Update | January 14, 2022

Posted on: January 14, 2022
American Tobacco Waterline Replacement

Project Update | January 7, 2022

Posted on: January 7, 2022
American Tobacco Waterline Replacement

Project Update | December 31, 2021

Posted on: December 31, 2021
American Tobacco Waterline Replacement

Project Update | December 24, 2021

Posted on: December 24, 2021
American Tobacco Waterline Replacement

Gregson Street Closure - January 10, 2022

Posted on: December 20, 2021
American Tobacco Waterline Replacement

Project Update | December 17, 2021

Posted on: December 17, 2021
American Tobacco Waterline Replacement

Project Update | December 10, 2021

Posted on: December 10, 2021
American Tobacco Waterline Replacement

Project Update | December 3, 2021

Posted on: December 3, 2021
American Tobacco Waterline Replacement

Project Update | November 26, 2021

Posted on: November 26, 2021
American Tobacco Waterline Replacement

Project Update | November 19, 2021

Posted on: November 19, 2021
American Tobacco Waterline Replacement

Project Update | November 12, 2021

Posted on: November 12, 2021
American Tobacco Waterline Replacement

Project Update | November 5

Posted on: November 5, 2021
American Tobacco Waterline Replacement

Project Update | October 29

Posted on: October 29, 2021
American Tobacco Waterline Replacement

Project Update | October 22

Posted on: October 22, 2021
American Tobacco Waterline Replacement

Project Update | October 15

Posted on: October 15, 2021
American Tobacco Waterline Replacement

Project Update | October 8

Posted on: October 8, 2021
American Tobacco Waterline Replacement

Project Update | October 1

Posted on: October 1, 2021
American Tobacco Waterline Replacement

Project Update | September 24

Posted on: September 24, 2021
American Tobacco Waterline Replacement

Project Update | September 17

Posted on: September 17, 2021
American Tobacco Waterline Replacement

Project Update | September 10

Posted on: September 10, 2021
American Tobacco Waterline Replacement

Project Update | September 3

Posted on: September 3, 2021
American Tobacco Waterline Replacement

Project Update | August 27

Posted on: August 27, 2021
American Tobacco Waterline Replacement

Project Update | August 20

Posted on: August 20, 2021
American Tobacco Waterline Replacement

Project Update | August 13

Posted on: August 13, 2021
American Tobacco Waterline Replacement

Project Update | August 6

Posted on: August 6, 2021

Project Update | July 30

Posted on: July 30, 2021
American Tobacco Waterline Replacement

Project Update | July 16

Posted on: July 16, 2021
American Tobacco Waterline Replacement

Project Update | July 9

Posted on: July 9, 2021
American Tobacco Waterline Replacement

Project Update | July 2

Posted on: July 2, 2021
American Tobacco Waterline Replacement

Project Update | June 25

Posted on: June 25, 2021
American Tobacco Waterline Replacement

Project Update | June 18

Posted on: June 18, 2021
American Tobacco Waterline Replacement

Project Update | June 11

Posted on: June 11, 2021
American Tobacco Waterline Replacement

Project Update | June 4

Posted on: June 4, 2021
American Tobacco Waterline Replacement

Project Update | May 28

Posted on: May 28, 2021
American Tobacco Waterline Replacement

Project Update | May 21

Posted on: May 21, 2021
American Tobacco Waterline Replacement

Project Update | May 14

Posted on: May 14, 2021
American Tobacco Waterline Replacement

Project Update | May 7

Posted on: May 7, 2021

Project Update | April 30

Posted on: April 30, 2021
American Tobacco Waterline Replacement

Project Update | April 23

Posted on: April 23, 2021
American Tobacco Waterline Replacement

Project Update | April 16

Posted on: April 16, 2021
American Tobacco Waterline Replacement

Project Update | April 9

Posted on: April 9, 2021
American Tobacco Waterline Replacement

Project Update | April 2

Posted on: April 2, 2021
American Tobacco Waterline Replacement

Project Update | March 26

Posted on: March 26, 2021
American Tobacco Waterline Replacement

Project Update | March 19

Posted on: March 19, 2021
American Tobacco Waterline Replacement

Project Update | March 12

Posted on: March 12, 2021