American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead
August 27, 2021
The City appreciates your ongoing patience with the work along the busy corridors associated with this project. Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.
Planned Road / Lane Closures will occur as follows:
- Week of 8/30:
- Lane closures and shifts in Chapel Hill Street between Gregson Street and Pettigrew Street.
- Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
- Lane closures and shifts in Gregson Street between Pettigrew Street and Chapel Hill Street.
- Week of 9/7:
- Lane closures and shifts in Chapel Hill Street between Gregson Street and Pettigrew Street.
- Lane closures and shifts in Duke Street between Yancey Street and Pettigrew Street.
- Lane closures and shifts in Gregson Street between Pettigrew Street and Chapel Hill Street.
Bicycle Lane and Sidewalk impacts will occur as follows:
- Dedicated bike lanes in Chapel Hill Street between Gregson and Pettigrew streets will be removed as part of roadway lane shifts.
- Varying sidewalk on the north and south sides of Chapel Hill Street between Gregson and Pettigrew streets will be closed to accommodate waterline installation.
- The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.
Saturday – Sunday August 28-29, 2021:
- No work will take place on Saturday or Sunday.
Week of August 30, 2021:
- Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
- Lane shifts in Duke Street between Yancey and Pettigrew streets using temporary pavement markings will be implemented.
- Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place near the Duke / Chapel Hill and Duke / Memorial intersections and at waterline connection locations.
- Traffic control signs and markings will be used for the lane closures and shifts.
- The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
- Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
- Lane shifts in Chapel Hill Street between Gregson and Pettigrew streets using temporary pavement markings are implemented.
- Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
- Traffic control signs and markings will be used for the lane closures and shifts.
- The sidewalk on the north side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
- Gregson Street between Pettigrew Street and Chapel Hill Street will have lane closures while work is taking place near the Chapel Hill Street / Gregson Street intersection.
- Lane shifts in Gregson Street between Pettigrew and Chapel Hill streets will be implemented between 9 AM and 4 PM.
- Traffic control signs and markings will be used for the lane closures and shifts.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours in Gregson Street are 9 AM to 4 PM.
- No water or sewer service disruptions are anticipated.
Saturday – Monday September 4-6, 2021:
- No work will take place on Saturday, Sunday, or Monday (Labor Day).
Week of September 7, 2021:
- Duke Street between Yancey Street / NC-147 and Pettigrew Street will have lane closures and traffic shifts to accommodate waterline installation.
- Lane shifts in Duke Street between Yancey and Pettigrew streets using temporary pavement markings will be implemented.
- Lane shifts with flaggers or temporary detours will be utilized for traffic control while work is taking place near the Duke / Chapel Hill and Duke / Memorial intersections and at waterline connection locations.
- Traffic control signs and markings will be used for the lane closures and shifts.
- The sidewalk on the west side of Duke Street between Yancey Street and Pettigrew Street will have temporary closures to accommodate waterline installation.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
- Chapel Hill Street between Gregson Street and Willard Street will have lane closures and traffic shifts to accommodate waterline installation.
- Lane shifts in Chapel Hill Street between Gregson and Pettigrew streets using temporary pavement markings are implemented.
- Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
- Traffic control signs and markings will be used for the lane closures and shifts.
- The sidewalk on the north side of Chapel Hill Street between Willard and Gregson streets will be closed to accommodate waterline installation.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours are 7 AM to 7 PM.
- No water or sewer service disruptions are anticipated.
- Gregson Street between Pettigrew Street and Chapel Hill Street will have lane closures while work is taking place near the Chapel Hill Street / Gregson Street intersection.
- Lane shifts in Gregson Street between Pettigrew and Chapel Hill streets will be implemented between 9 AM and 4 PM.
- Traffic control signs and markings will be used for the lane closures and shifts.
- Noise levels in excess of the current City noise ordinance are anticipated during work hours.
- Planned work hours in Gregson Street are 9 AM to 4 PM.
- No water or sewer service disruptions are anticipated.
Saturday – Sunday September 11-12, 2021:
- No work will take place on Saturday or Sunday.
If you have questions, please email [email protected].
Service request:
Click or call 919-560-1200