Project Updates: American Tobacco District Waterline Replacement

Posted on: April 15, 2022

[ARCHIVED] Project Update | April 15, 2022

American Tobacco Waterline Replacement

American Tobacco District Waterline Replacement – Phase 1 Project Update and Two-Week Look Ahead

April 15, 2022

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 4/18: 
    • Lane closures and shifts in Peabody Street between Main Street and Duke Street.
    • Lane closures and shifts in Chapel Hill Street between NC-147 and Gregson Street.
    • Lane closures in Jackson Street between Gregson Street and William Vickers Ave, and William Vickers Ave between Jackson Street and Chapel Hill Street.
  • Week of 4/25: 
    • Lane closures and shifts in Peabody Street between Main Street and Duke Street.
    • Lane closures and shifts in Chapel Hill Street between NC-147 and Gregson Street.
    • Lane closures in Jackson Street between Gregson Street and William Vickers Ave, and William Vickers Ave between Jackson Street and Chapel Hill Street.

Bicycle Lane and Sidewalk impacts will occur as follows:

  • Portions of the sidewalk and bicycle lane on the south side of Chapel Hill Street between Shepherd Street and Gregson Street will have temporary closures to accommodate waterline installation.

Saturday – Sunday April 16-17, 2022:

  • No work is planned on Saturday or Sunday.

Week of April 18, 2022:

  • Peabody Street between Main Street and Duke Street will have local road and lane closures to accommodate waterline installation.
    • Traffic control signs and markings will be used for the road and lane closures, including at the Gregson / Peabody and Duke / Peabody intersections.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Peabody Street between Main Street and Gregson Street will have isolated closures with local access being maintained.
    • Pavement along Peabody Street will be rough and uneven as final pavement repairs are being completed.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between NC-147 and Duke Street will have lane closures and shifts to accommodate waterline installation and pavement restoration.
    • Traffic control signs and markings will be used for the lane closures and shifts, including at the Chapel Hill / William Vickers and Chapel Hill / Gregson intersections.
    • On-street parking on the south side of Chapel Hill Street will be temporarily closed in active work areas.
    • Pavement along Chapel Hill Street will be rough and uneven as final pavement repairs are being completed.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Jackson Street between Gregson Street and William Vickers Ave, and William Vickers Ave between Jackson Street and Chapel Hill Street will have lane closures and traffic shifts to accommodate waterline installation, pavement restoration, and sanitary sewer rehabilitation.
    • Traffic control signs and markings will be used for the lane closures and shifts.  Northbound traffic on William Vickers Ave will be maintained.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Pavement along Jackson St and William Vickers Ave will be rough and uneven as final pavement repairs are being completed.
    • Sanitary sewer rehabilitation and lining will take place.  The rehabilitation schedule will be coordinated with customers in vicinity of the sewer being rehabilitated.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.

Saturday – Sunday April 23-24, 2022:

  • No work is planned on Saturday or Sunday.

Week of April 25, 2022:

  • Peabody Street between Main Street and Duke Street will have local road and lane closures to accommodate waterline installation.
    • Traffic control signs and markings will be used for the road and lane closures, including at the Gregson / Peabody and Duke / Peabody intersections.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Peabody Street between Main Street and Gregson Street will have isolated closures with local access being maintained.
    • Pavement along Peabody Street will be rough and uneven as final pavement repairs are being completed.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Chapel Hill Street between NC-147 and Duke Street will have lane closures and shifts to accommodate waterline installation and pavement restoration.
    • Traffic control signs and markings will be used for the lane closures and shifts, including at the Chapel Hill / William Vickers and Chapel Hill / Gregson intersections.
    • On-street parking on the south side of Chapel Hill Street will be temporarily closed in active work areas.
    • Pavement along Chapel Hill Street will be rough and uneven as final pavement repairs are being completed.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Jackson Street between Gregson Street and William Vickers Ave, and William Vickers Ave between Jackson Street and Chapel Hill Street will have lane closures and traffic shifts to accommodate waterline installation and pavement restoration.
    • Traffic control signs and markings will be used for the lane closures and shifts.  Northbound traffic on William Vickers Ave will be maintained.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Pavement along Jackson St and William Vickers Ave will be rough and uneven as final pavement repairs are being completed.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.

Saturday – Sunday April 30-31, 2022:

  • No work is planned on Saturday or Sunday.

If you have questions, please email [email protected].

Facebook Twitter Email

Other News in Project Updates: American Tobacco District Waterline Replacement

American Tobacco Waterline Replacement

Project Update | February 1, 2023

Posted on: February 1, 2023
American Tobacco Waterline Replacement

Project Update | March 11, 2022

Posted on: March 11, 2022
American Tobacco Waterline Replacement

Project Update | March 4, 2022

Posted on: March 4, 2022
American Tobacco Waterline Replacement

Project Update | February 25, 2022

Posted on: February 25, 2022
American Tobacco Waterline Replacement

Project Update | February 18, 2022

Posted on: February 18, 2022
American Tobacco Waterline Replacement

Project Update | February 11, 2022

Posted on: February 11, 2022
American Tobacco Waterline Replacement

Project Update | February 4, 2022

Posted on: February 4, 2022
American Tobacco Waterline Replacement

Project Update | January 28, 2022

Posted on: January 28, 2022
American Tobacco Waterline Replacement

Project Update | January 21, 2022

Posted on: January 21, 2022
American Tobacco Waterline Replacement

Project Update | January 14, 2022

Posted on: January 14, 2022
American Tobacco Waterline Replacement

Project Update | January 7, 2022

Posted on: January 7, 2022
American Tobacco Waterline Replacement

Project Update | December 31, 2021

Posted on: December 31, 2021
American Tobacco Waterline Replacement

Project Update | December 24, 2021

Posted on: December 24, 2021
American Tobacco Waterline Replacement

Gregson Street Closure - January 10, 2022

Posted on: December 20, 2021
American Tobacco Waterline Replacement

Project Update | December 17, 2021

Posted on: December 17, 2021
American Tobacco Waterline Replacement

Project Update | December 10, 2021

Posted on: December 10, 2021
American Tobacco Waterline Replacement

Project Update | December 3, 2021

Posted on: December 3, 2021
American Tobacco Waterline Replacement

Project Update | November 26, 2021

Posted on: November 26, 2021
American Tobacco Waterline Replacement

Project Update | November 19, 2021

Posted on: November 19, 2021
American Tobacco Waterline Replacement

Project Update | November 12, 2021

Posted on: November 12, 2021
American Tobacco Waterline Replacement

Project Update | November 5

Posted on: November 5, 2021
American Tobacco Waterline Replacement

Project Update | October 29

Posted on: October 29, 2021
American Tobacco Waterline Replacement

Project Update | October 22

Posted on: October 22, 2021
American Tobacco Waterline Replacement

Project Update | October 15

Posted on: October 15, 2021
American Tobacco Waterline Replacement

Project Update | October 8

Posted on: October 8, 2021
American Tobacco Waterline Replacement

Project Update | October 1

Posted on: October 1, 2021
American Tobacco Waterline Replacement

Project Update | September 24

Posted on: September 24, 2021
American Tobacco Waterline Replacement

Project Update | September 17

Posted on: September 17, 2021
American Tobacco Waterline Replacement

Project Update | September 10

Posted on: September 10, 2021
American Tobacco Waterline Replacement

Project Update | September 3

Posted on: September 3, 2021
American Tobacco Waterline Replacement

Project Update | August 27

Posted on: August 27, 2021
American Tobacco Waterline Replacement

Project Update | August 20

Posted on: August 20, 2021
American Tobacco Waterline Replacement

Project Update | August 13

Posted on: August 13, 2021
American Tobacco Waterline Replacement

Project Update | August 6

Posted on: August 6, 2021

Project Update | July 30

Posted on: July 30, 2021
American Tobacco Waterline Replacement

Project Update | July 23

Posted on: July 23, 2021
American Tobacco Waterline Replacement

Project Update | July 16

Posted on: July 16, 2021
American Tobacco Waterline Replacement

Project Update | July 9

Posted on: July 9, 2021
American Tobacco Waterline Replacement

Project Update | July 2

Posted on: July 2, 2021
American Tobacco Waterline Replacement

Project Update | June 25

Posted on: June 25, 2021
American Tobacco Waterline Replacement

Project Update | June 18

Posted on: June 18, 2021
American Tobacco Waterline Replacement

Project Update | June 11

Posted on: June 11, 2021
American Tobacco Waterline Replacement

Project Update | June 4

Posted on: June 4, 2021
American Tobacco Waterline Replacement

Project Update | May 28

Posted on: May 28, 2021
American Tobacco Waterline Replacement

Project Update | May 21

Posted on: May 21, 2021
American Tobacco Waterline Replacement

Project Update | May 14

Posted on: May 14, 2021
American Tobacco Waterline Replacement

Project Update | May 7

Posted on: May 7, 2021

Project Update | April 30

Posted on: April 30, 2021
American Tobacco Waterline Replacement

Project Update | April 23

Posted on: April 23, 2021
American Tobacco Waterline Replacement

Project Update | April 16

Posted on: April 16, 2021
American Tobacco Waterline Replacement

Project Update | April 9

Posted on: April 9, 2021
American Tobacco Waterline Replacement

Project Update | April 2

Posted on: April 2, 2021
American Tobacco Waterline Replacement

Project Update | March 26

Posted on: March 26, 2021
American Tobacco Waterline Replacement

Project Update | March 19

Posted on: March 19, 2021
American Tobacco Waterline Replacement

Project Update | March 12

Posted on: March 12, 2021