Roadway Section Closed on April 25 to Traffic Until Construction Completed
On April 25, the City of Durham Public Works Department will begin an emergency construction project to replace a compromised stormwater culvert within the Carpenter Fletcher Road right-of-way between N.C. Hwy. 55 and Loyal Avenue.
This section of Carpenter Fletcher Road will be closed to traffic on April 25 and will remain closed until the construction of the culvert and roadway replacement is complete. The City’s Transportation Department has created a traffic detour via North Bend Drive to Meridian Parkway to N.C. Hwy. 55 (see image below).
Construction of the replacement stormwater culvert and roadway is expected to take approximately 60 days depending upon weather conditions. The cost to reconstruct the culvert and roadway is estimated at $223,000 and will be paid for through Stormwater Capital Improvement Program (CIP) funds.
For more information about this emergency repair project, contact Project Manager Donald Perry with the City's Public Works Department by phone at (919) 560-4326, ext. 30246 or by email.
About the Public Works Department Stormwater and GIS Services Division
The Stormwater and GIS Services Division with the City of Durham Public Works Department is guided by the City’s Strategic Plan goals of sustainable natural, and built environment and innovative and high-performing organization. Activities include storm drainage design and plans review; inspecting and maintaining City-owned drainage systems; enforcing stormwater ordinances and regulations; education and outreach; stream monitoring, restoration, and watershed master planning; maintaining multiple layers of the City’s geographic information; and stormwater billing. To learn more, visit the division’s webpage and follow on Facebook and Twitter.
Carpenter Fletcher Detour Route:

Service request:
Click or call 919-560-1200