News Flash

Project Updates: Lakewood Avenue Sewer Replacement

Posted on: September 1, 2023

Project Update | September 1, 2023

Graphic with text that reads Lakewood Ave Sanitary Sewer Replacement Construction Update

Lakewood Avenue Sanitary Sewer Replacement Project Construction Look Ahead – Upcoming Road Closure

September 1, 2023

The City appreciates your ongoing patience with the work along the busy corridors associated with this project.  Additional information regarding this project can be found at: https://www.durhamnc.gov/3976/Lakewood-Avenue-Sewer-Replacement-Projec.

Beginning the week of September 5, Roxboro Street will have lane closures between Hillside Ave and Morehead Ave for approximately 4 to 5 months to accommodate sanitary sewer and waterline installations.  

Beginning the week of September 11, Lakewood Avenue will be closed with detours between Mangum Street and Roxboro Street for approximately 2 to 3 months to accommodate sanitary sewer and waterline installations.  

Additional information about the work and planned impacts are described below.

Planned Road / Lane Closures will occur as follows:

  • Week of 9/5: 
    • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections.
    • Lane shifts in Lakewood Avenue between Mangum Street and Roxboro Street.
    • Lane shifts in Roxboro Street between Hillside Avenue and Morehead Avenue.
  • Week of 9/11: 
    • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections.
    • Road closure in Lakewood Avenue between Mangum Street and Roxboro Street.
    • Lane shifts in Roxboro Street between Hillside Avenue and Morehead Avenue.
  • Future Week(s): 
    • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections.
    • The Lakewood Avenue road closure is anticipated to remain in place for approximately 2-3 months.
    • The Roxboro Street lane shifts are anticipated to remain in place for approximately 4-5 months.

Bicycle Lane and Sidewalk impacts will occur as follows:

  • Portions of the sidewalk along University Drive near the Duke Street and W Lakewood Ave intersections will have temporary closures.
  • Portions of the sidewalk near work areas along Lakewood Ave and Roxboro Street will have temporary closures.

Saturday, Sunday, and Monday (Labor Day) – September 2-4, 2023:

  • A sanitary sewer bypass will be used to accommodate the next phase of sewer installation.  
    • Pumps and piping with on-site observation will be used 24 hours a day, 7 days a week. 
    • Noise levels in accordance with the City noise ordinance are anticipated.  

Week of September 5, 2023:

  • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections will be in place to accommodate sanitary sewer installation.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • W Lakewood Ave between University Drive and Duke Street will be closed.  
    • Temporary pavement markings will be installed to shift traffic lanes along University Drive.
    • Sanitary sewer installations will and continue along a cross country corridor outside of Lakewood Ave.
    • Noise levels in excess of the current City noise ordinance are anticipated during daytime work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
    • A sanitary sewer bypass will be used to accommodate this phase of sewer installation.  Pumps and piping with on-site observation will be used 24 hours a day, 7 days a week. 
  • Lakewood Avenue lane shifts between Mangum St and Roxboro St to accommodate sanitary sewer and waterline installation.
    • Traffic control signs and markings will be used for the lane closures and shifts.  
    • Flaggers will be used in Lakewood Ave between the hours of 9 AM and 4 PM to maintain traffic in both directions.
    • Sidewalk traffic will be disrupted in this area.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Roxboro Street lane shifts between Hillside Ave and Morehead Ave to accommodate sanitary sewer and waterline installation.
    • Traffic control signs and markings will be used for the lane closures and shifts.  Northbound Roxboro St traffic will be maintained.
    • Temporary pavement markings will be installed to shift traffic lanes along Roxboro St.
    • Sidewalk traffic will be disrupted in this area.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday and Sunday – September 9-10, 2023:

  • A sanitary sewer bypass will be used to accommodate the next phase of sewer installation.  
    • Pumps and piping with on-site observation will be used 24 hours a day, 7 days a week. 
    • Noise levels in accordance with the City noise ordinance are anticipated.  

Week of September 11, 2023:

  • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections will be in place to accommodate sanitary sewer installation.
    • Traffic control signs and markings will be used for the lane closures and shifts.
    • W Lakewood Ave between University Drive and Duke Street will be closed.  
    • Temporary pavement markings will be installed to shift traffic lanes along University Drive.
    • Sanitary sewer installations will and continue along a cross country corridor outside of Lakewood Ave.
    • Noise levels in excess of the current City noise ordinance are anticipated during daytime work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
    • A sanitary sewer bypass will be used to accommodate this phase of sewer installation.  Pumps and piping with on-site observation will be used 24 hours a day, 7 days a week. 
  • Lakewood Avenue will be closed between Mangum St and Roxboro St to accommodate sanitary sewer and waterline installation.
    • Traffic control signs and markings will be used a detour of traffic along Lakewood Avenue.  
    • Northbound traffic will be detoured using Blackwell St, Morehead Ave, and the Mangum Roxboro Connector.
    • Southbound traffic will be detoured using Roxboro St, Jackie Robinson Dr, and Mangum St.
    • Sidewalk traffic will be disrupted in this area.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Roxboro Street lane shifts will be implemented between Hillside Ave and Morehead Ave to accommodate sanitary sewer and waterline installation.
    • Traffic control signs and markings will be used for the lane closures and shifts.  Northbound Roxboro St traffic will be maintained.
    • Temporary pavement markings will be installed to shift traffic lanes along Roxboro St.
    • Sidewalk traffic will be disrupted in this area.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated. 

Saturday and Sunday – September 16-17, 2023:

  • A sanitary sewer bypass will be used to accommodate the next phase of sewer installation.  
    • Pumps and piping with on-site observation will be used 24 hours a day, 7 days a week. 
    • Noise levels in accordance with the City noise ordinance are anticipated.  

Projected Future Work (pending progress and weather):

  • Lane closures and shifts along University Drive / Lakewood Avenue near the Duke Street intersection and W Lakewood Ave intersections will remain in place to accommodate sanitary sewer installation.
  • Lakewood Avenue will remain closed for approximately 2 to 3 months between Mangum St and Roxboro St to accommodate sanitary sewer and waterline installation.  
    • Additional closures of Lakewood Avenue between Duke Street and Mangum Street will be required in coming months.  Further details about this phase of work will be provided in the future.
  • Roxboro Street lane shifts will remain in place for 4 to 5 months to accommodate sanitary sewer and waterline installation.  

If you have questions, please email [email protected].